Last week saw great progress at the Glebe Farm site. On Monday 13th the erection team arrived and started to install the framework for the ground mounted panels. By Monday 20th the framework was all in place and the 1000 panels were all bolted to the framework. The next stage is to wire all the panels to to the inverters and put in place the cables to connect to the buildings. All running well to schedule at present.