Last week saw the plinth for the inverter shed laid and all the trenches for the cable dug – from the panels to the inverter shed and from the inverter shed to the buildings where the electricity will be used. This week should see the panels strung together and the cables laid in the trenches.
Western Power Distribution are installing a new HV transformer on site which is needed to allow us to export the full capacity. They cannot install this until August, but we will be able to connect up part of the site before this, and are working on getting the one set of 140kW connected before the end of June, with the remainder of the panels to be connected as soon as the Western Power transformer is in place.